Adding actuals into progress entry

It would be really helpful to be able to see the actuals applied to the phase in the progress entry form. 

  • Guest
  • Aug 20 2019
  • Future consideration
Company ATG
Job Title / Role Data Systems Manager
I need it... Yesterday...Come on already
  • Attach files
  • Kayla Pickett commented
    May 05, 2022 17:51

    We would love to see the actual hours column, in progress entry. This is one thing that has been requested by many of our branch offices.

  • Admin
    Mark Cadman commented
    November 26, 2019 21:55

    Hi Lindsay,

    We don't show Actual Hours anywhere on Progress Entry, the other fields we are showing pull from the following places:

    Factor = udFactor on JC Original Estimates (if blank or not in Vista, will default to 1)

    QTY = udQTY on JC Original Estimates (if blank or not in Vista, will default to 1)

    Total Hours = QTY * Factor * Current Estimated Hours

    Hours Allowed = Total % Completed * Total Hours

    Let's see how the community feels about adding the Actual Hours column to this page in the portal.

    Thank you!

  • Guest commented
    October 07, 2019 00:36

    Hi Mark,

    Sorry for the delayed response, for so reason this email keeps going to my junk mail. I changed the portal setting but it is still not showing the correct actual hours when compared to the information in Vista. It should show 4 actual hours processed through PR but it���s not.

    [cid:image001.jpg@01D57C6C.362F7650]

    Thanks,

    Lindsey Jones-Robinson
    455 SE 2nd Avenue, Hillsboro, OR 97123
    M: 443.717.4155
    LindseyJ-R@atgweb.com
    atgweb.com
    [cid:image002.png@01D57C6C.362F7650]

  • Admin
    Mark Cadman commented
    October 04, 2019 15:16

    Hi Lindsey,

    It looks like you are currently hiding the "Completed" column with your current portal setup. Can you disable the "Hide Completed, Newly Completed, and Total Completed columns" portal setting?

    The Hours Allowed, Total Hours, Quantify, and Factor are all related to this portal setting "Show Quantity, Factor, Total Hours, and Hours Allowed"

    Are you using these fields?

  • Guest commented
    October 04, 2019 14:37

    HI Mark,

    No our progress entries do not show the total actual hours applied. We���re actually are having an issue with Progress Entry currently that I���ve open a case for. Below is an example of what we see in Vista verse Progress.

    The estimated Units and Total Hour show what we have estimated. The Total completed % is what I have open a case about as starting this week Total Complete % has been showing values that we never entered.
    I���m also not sure where the Hours Allowed is coming from. It maybe showing the orginal estimated hours and not accounting for the change or to reduce the estimate hours as funding was removed from this phase?
    [cid:image004.jpg@01D57A86.316AD930]

    This is a standard report from Vista. It shows the estimated hours (2.01) and the actual hour applied (4). I���m am not seeing the actual hours on the progress entry.
    [cid:image005.jpg@01D57A86.316AD930]
    Thanks,

    Lindsey Jones-Robinson
    455 SE 2nd Avenue, Hillsboro, OR 97123
    M: 443.717.4155
    LindseyJ-R@atgweb.com
    atgweb.com
    [cid:image003.png@01D57A85.AEC12430]

  • Admin
    Mark Cadman commented
    October 04, 2019 02:21

    Hi Lindsey,

    The Completed column should show the Actual Units completed. Are you seeing something different in your portal?

  • Guest commented
    August 22, 2019 15:23

    Having the actual units that have been processed in Vista would make it so that our employees who are entering Progress Entry don't have to look at other reports, like JC Costs/Estimates by Project Manager, in order to see the actuals have been applied to the phase. 

Dear Viewpoint Suggestion Box contributor;

We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs. Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.

1515 SE Water Avenue, Suite 300, Portland, OR 97214 |  800.333.3197  | Contact Us | Terms of Use | Privacy | Support Policies

© 2024 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.