It would be great if we could see the Estimated Production Rate next to the Estimated Units in Progress Entry (portal). Also, we would like the Actual Production Rate to calculate after the Completed Units are entered (next to the Daily Over/Under). It would be great to be able to see all of this in one place instead of going to other sources to pull similar information.
Company | Western Group |
Job Title / Role | IT Systems Trainer |
I need it... | Yesterday...Come on already |
Dear Viewpoint Suggestion Box contributor;
We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs.
Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.
© 2024 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.
Anytime Kayla!
Hi Mark,
I think this setting works for what we need. Thank you for your help.
Hi Kayla,
For the Estimated Production Rate, we can show the current Units / Hour based on the JC Original Estimates by enabling the "Show Units/Hour on Grid" portal setting.
For the Actual Production, would you like us to pull all labor hours on that phase for that day that are currently in the Vista PR Timecard Entry batch?
The Field Ticket has this level of detailed information today. If we showed what we currently show in Field Tickets in Progress Entry, would that meet your needs?
Thanks!
Hi Mark,
I'm referring to the actual production rate to mean the current completed units/current hours after the progress has been entered into progress entry. That way they can see it before the production gets submitted.
Hi Kayla,
When you say Actual Production Rate do you mean the current completed units / current hours puling from what's been processed in Vista?
Thanks